Three weeks into the AUKUS Osborne Utilities Relocation Project, construction works have destroyed substantial areas of saltmarsh and mangroves at Mutton Cove on the Port River.
The project has been required by Australian Naval Infrastructure (ANI), so that the existing gas and electricity lines are located further from the proposed site for the nuclear submarines build, and a new substation built, as outlined here. That involves trenching through Mutton Cove for the gas and electricity lines and taking Mutton Cove land for the new substation.
During the first two weeks of construction FPR saw substantial loss of saltmarsh. Now in week 3, a large swathe of mangroves have been cut down.
There was no independent environmental assessment of the impact of the Project, after ANI submitted but then withdrew its referral under the EPBC Act in 2025. There was no publicly available information about the nature and extent of the work to be undertaken in trenching to relocate the gas lines. The recent Development Application approved by Minister Champion on 23rd October again gave no indication of the scale of destruction involved.
The Assessment Report from the Department of Housing and Urban Development (DHUD) told the State Commission Assessment Panel (SCAP) that “The proposal does not require a referral under the Environment Protection and Biodiversity Conservation Act (Cwth) 1999 (EPBC Act)”.
The same document gave this description of Mutton Cove: “Mutton Cove (part 778 Mersey Road N) – a 48-ha conservation reserve on Crown Land and under the management of the Department for Environment and Water (DEW). The reserve hosts salt marsh and Grey Mangrove woodland and features two heritage listed shipwrecks”. These were the only reference to mangrove(s) and saltmarsh (salt marsh) in the document.
Friends of Port River (FPR) and Port Adelaide Environment Protection Group (PAREPG) submitted our concerns in response to the Development Application and presented to SCAP. At that stage we thought it was the saltmarsh at risk, and submitted these (and other) photos to SCAP showing the vegetation, as it was. Little did we know that it was also the mangroves, in the middle of the first photo, that were also to be removed.



For ten years, since the Port River seawall was breached in 2016 (after the SA Government failed to maintain it) FPR and PAREPG have worked for recognition of the environmental and community value of Mutton Cove, seeking action to prevent its total inundation. Instead we get saltmarsh and mangroves destroyed.
Friends of Port River are grateful to Greens MLC Melanie Selwood for asking this question of the SA Minister for Climate, Environment and Water on November 25th. No answers forthcoming as yet!